# Concreting Checklist Guide

How a site team checks formwork, rebar, materials and safety before pouring a concrete floor slab, then pours, tests and cures it\.

By agni veer

Topic: Home &amp; DIY

[Open the interactive Jig](https://ask.jig.com/j/nrD3m2AcDIwi)

## Transcript

### 1. Before the pour

Once concrete is poured, it cannot be taken back\. So before the mixer truck arrives, the site team walks through a checklist, one section at a time\. Let's follow it on this floor slab, waiting to be cast\.

Floor slabs are often 100 to 500 mm thick\. This one is 150 mm\.

### 2. Form work

Formwork is the temporary mould that shapes the concrete\. Inspectors check its size, level and plumb \(truly upright\), and that it is tight, rigid and clean\. Edge boards close the sides, release agent coats the deck, and the scaffolding plan must be approved\.

Release agent is a thin oily coat that stops concrete sticking, so the boards can be reused\.

### 3. Rebar

Steel bars, called rebar, help concrete resist bending and stretching\. A bar bending schedule \(BBS\) lists every bar, so inspectors count the bars and the laps, where two bars overlap to join\. Bars must be clean, tied firmly and raised on cover blocks\.

The concrete "cover" under and around the bars protects the steel from rust and fire\.

### 4. Openings and hidden pipes

Anything that must pass through the slab goes in now\. Box\-outs leave square openings, pipe sleeves leave round holes, and electrical conduits are laid inside\. Drilling through hardened concrete and steel later would be slow and risky\.

Expansion joints, gaps that let concrete grow and shrink, are also fixed now if the drawings call for them\.

### 5. Materials and old concrete

The ready\-mixed concrete \(RMC\) and any plasticisers, additives that help it flow, are checked against the order\. Where new concrete meets old, the old surface is roughened, or hacked, and cleaned so the two bond\. Lights are set up in case the pour runs late\.

Adding extra water makes concrete easier to pour but weaker\.

### 6. Safety first

Everyone gets PPE, personal protective equipment such as helmets, boots and gloves\. Workers need a safe platform with guard rails, safety nets, a safe way up, a known emergency exit and safe electrics\.

Wet concrete is strongly alkaline and can irritate skin, so gloves and boots really matter\.

### 7. Clearance and slump test

With every section ticked, the engineers give clearance and the mixer truck arrives\. In a slump test a cone is filled, lifted away, and the drop of the concrete is measured in millimetres\. Test cubes are filled too, to be crushed in a lab later\.

A stiff mix may slump about 25 to 50 mm; a very runny one up to about 200 mm\.

### 8. Pour and vibrate

The concrete is pumped in and spread across the deck\. A poker vibrator shakes out trapped air so the concrete fills every corner and wraps every bar\. The pour's start and end times go on the checklist\.

### 9. After the pour

The surface is levelled to the right line and level, and the formwork is checked to be still steady\. Then the slab is kept wet, for example by ponding water on top, while it cures\. Concrete hardens by a chemical reaction with water, not by drying out\.

After about four weeks it is over 90% as strong as it will get, and the test cubes prove it\.